Resumo
NARAIN SINGH, S e PRETORIUS, J.H.C. Development of a Sem-Quantitative approach for risk based inspection and maintenance of thermal power plant components. SAIEE ARJ [online]. 2017, vol.108, n.3, pp.128-137. ISSN 1991-1696.
This paper deals with the development of a semi-quantitative Risk Based Inspection programmes for the Eskom fossil fired generating fleet. This study comes as a result of internal and external factors that affect Eskom from producing electricity in a safe, sustainable manner to ensure security of electricity supply. Eskom has embarked on a risk based maintenance approach to meet the statutory and safety requirements as stipulated by the Depart of Labour as well as to potentially reduce outage costs. The European CWA15740 approach was used to develop the Risk Based Management System.
Palavras-chave : Risk Based Inspection; Probability of Failure; Consequence of Failure; Component damage mechanism; Pressure Equipment Regulation; Multi Level Risk Assessment; Pressure Equipment Regulation (PER); Risk Based Inspection and Maintenance Application Procedures (RIMAP); Energy Availability Factor (EAF); Unplanned Unit Capability Loss Factor (UCLF); Planned Unit Capability Loss Factor (PCLF).
![](/img/en/iconPDFDocument.gif)