    Acta Structilia

    On-line version ISSN 2415-0487
    Print version ISSN 1023-0564

    Acta structilia (Online) vol.28 n.1 Bloemfontein  2021

    http://dx.doi.org/10.18820/24150487/as28i1.6 

    RESEARCH ARTICLES · NAVORSINGSARTIKELS

     

    The effect of poor materials management in the construction industry: a case study of Abuja, Nigeria

     

     

    Mr Idowu AlbertI; Prof. Winston ShakantuII; Dr Saidu IbrahimIII

    IDepartment of Construction Management, Nelson Mandela University, Port Elizabeth, South Africa, Email: <idowualbertino@yahoo.com>
    IIDepartment of Construction Management, Nelson Mandela University, Port Elizabeth, South Africa, email: <winston.shakantu@mandela.ac.za> ORCID: https://orcid.org/0000-0002-4334-5004
    IIIDepartment of Quantity Survey, Federal University of Technology, PMB 39, Niger Minna, State Nigeria. Phone: +234 8037796321, email: <saidu.ibr@futminna.edu.ng>

     

     


    ABSTRACT

    Effective materials management on construction sites is handled carelessly by construction practitioners. This may result in several challenges such as materials waste generation, poor quality of work, project delays, and poor materials flow. Construction practitioners in Abuja, Nigeria, do not understand the consequences of these challenges to construction projects. This article investigates the effect of poor materials management on materials waste, quality of work, and project profitability in construction projects in Nigeria. A qualitative research approach was adopted in the study which included collective case study investigations. The population for the study was ongoing building project sites (ten case studies purposefully selected) in Abuja. The research instrument was direct-covert observation by the researchers to observe and record the construction processes, people's behaviour, actions and interactions relating to materials management. The construction processes observed included materials usage onsite, loading/ offloading of materials from procurement, storages, as well as materials handling and movement on site. Recording sheets with checklists were pre-set with statements (Likert items) and responses to observe and document the effect of poor materials management. The statements were rated on an ordinal three-point Likert scale. The observed/collected data were analysed using descriptive methods to determine the modal values. The findings from the study revealed that poor materials management has a considerable effect on material waste generation on any construction project site; moderate effects on quality of building projects, and both considerable and moderate effects on profitability in the construction projects. Based on these findings, it can be concluded that effective management of materials in construction projects would reduce the amount of waste generation, increase the quality of construction work, and offer optimum profitability to construction contractors. It is, therefore, recommended that the construction industry in Nigeria should collaborate with government agencies to develop guidelines for preparing a waste management plan for the construction industry.

    Keywords: Building materials, construction industry, materials management, poor materials management


    ABSTRAK

    Effektiewe materiaalbestuur op konstruksieterreine word onverskillig deur konstruksiepraktisyns hanteer. Dit kan lei tot verskeie uitdagings soos die opwekking van materiaalafval, swak gehalte werk, vertragings in die projek en swak vloei van materiaal. Die konstruksiepraktisyns in Abuja, Nigerië, verstaan nie die gevolge van hierdie uitdagings vir bouprojekte nie. Hierdie artikel ondersoek die effek van swak materiaalbestuur op materiaalafval, kwaliteit van die werk en projekwinsgewendheid in konstruksieprojekte in Nigerië. 'n Kwalitatiewe navorsingsbenadering is in die studie gebruik, wat kollektiewe gevallestudie-ondersoeke insluit. Die bevolking vir die studie was deurlopende bouprojekpersele (tien gevallestudies wat doelgerig gekies is) in Abuja. Die navorsingsinstrument was direkte-geheime waarneming deur die navorser om die konstruksieprosesse, mense se gedrag, optrede en interaksies wat met materiaalbestuur verband hou, waar te neem en op te teken. Die opgemerkte konstruksieprosesse sluit in die gebruik van materiaal op die terrein, laai/aflaai van materiaal vanaf verkryging, opbergings, en materiaalhantering en -beweging op die terrein. Optekenblaaie met kontrolelyste is vooraf opgestel met stellings (Likert-items) en antwoorde om die effek van swak materiaalbestuur waar te neem en te dokumenteer. Die stellings is op 'n gewone drie-punt Likert-skaal beoordeel. Die waargenome/versamelde data is geanaliseer met behulp van beskrywende metodes om die modale waardes te bepaal. Die bevindinge uit die studie het getoon dat swak materiaalbestuur 'n groot uitwerking het op die opwekking van materiaalafval op enige konstruksieprojek; matige effekte op die kwaliteit van bouprojekte; en beide 'n groot en matige uitwerking op winsgewendheid in die bouprojekte. Op grond van hierdie bevindings kan die gevolgtrekking gemaak word dat effektiewe bestuur van materiale in die konstruksieprojek sal lei tot die vermindering van die hoeveelheid afvalopwekking, verhoogde gehalte van konstruksiewerk en optimale winsgewendheid vir konstruksie-kontrakteurs. Dit word dus aanbeveel dat die konstruksiebedryf in Nigerië saamwerk met regeringsinstansies om riglyne te ontwikkel vir die opstel van 'n afvalbestuursplan vir die konstruksiebedryf.

    Sleutelwoorde: Boumateriaal, konstruksiebedryf, materiaalbestuur, swak materiaalbestuur


     

     

    1. INTRODUCTION

    The Nigerian construction sector plays an important role in the economic development of the country, as it has contributed roughly half of the total stock of fixed capital investment in the Nigerian economy (Ugwu & Attah, 2016: 754; Wahab, 2010: 94). The cost of construction materials may be 50% to 70% of the total construction expenditure, depending on the type of construction project (Arijeloye & Akinradewo, 2016: 169; Albert, 2014: 2; Patel & Vyas, 2011: 1).

    Construction waste has been identified as one of the major problems in the Nigerian construction industry that presents significant implications for the efficiency in the industry as well as the adverse impacts on the environment (Muleya & Kamalondo, 2017: 2). Sources of waste include unused materials, incorrect materials, surplus stencils or nails, packages of construction materials or components, surplus concrete materials resulting from fractures or deformations, due to improper storage or preservation of construction materials and components arriving at the construction site (Albert & Shakantu, 2017: 10). Others include poor materials handling, resulting in breakage; erroneous cuttings, increasing quantities of waste; improper or faulty equipment, delaying project completion; poor storage facilities, making it difficult to coordinate the storage requirements for the various subcontractors; poor workmanship, impacting negatively on the quality standard set up by management, and inaccurate measurements, leading to poor accounting for materials (Aziz & Hafez, 2013: 683).

    Managing materials on construction sites is a serious issue among Nigerian subcontractors. Sometimes, materials on site need to be moved from one place to another, resulting in additional costs (Arijeloye & Akinradewo, 2016: 175). The difficulty in storing materials on site, due to limited space, is another problem in Nigerian construction material management. Sometimes, machinery cannot be adjusted on site, due to space or mismanagement of site activities. Many construction projects apply manual methods for tracking materials, and this involves paper-based techniques that can become problematic, due to many human errors (Kasim, Latiffi & Fathi, 2013: 7). Albert and Shakantu (2017: 9) posit that the construction process depends on having the right people with the appropriate skills who are able to deliver the project on time and on budget.

    Therefore, the main goal of this study was to investigate the effect of poor materials management (PMM) in the Nigerian construction industry, with a view to enhancing site materials management and reducing waste. Without identifying the effect of PMM on materials waste, quality of work and project profitability, it may be difficult to enhance site materials management and reduce waste in the Nigerian construction industry.

     

    2. LITERATURE REVIEW

    2.1 Materials management in the construction industry

    Materials management is defined as the process to provide the right material to the right place on time and in the right quantity, in order to minimize the cost of a project (Kulkarni, Sharma & Hote, 2017: 475). The main goal of materials management is to ensure a smooth flow of materials from the time the materials are ordered until they are used. In order to make materials management on site effective, a proper integrated materials handling process that includes the planning, identification, procuring, storage, receiving and distribution of material, should be in place (Dallasega & Rauch, 2017: 1888).

    The construction industry involves the physical erection of structures using construction equipment, materials, supplies, supervision, and management that are necessary to accomplish the project (Clough, Sears & Sears, 2000). It involves many organisations such as clients or owners, architects, engineers, contractors, suppliers and vendors. It also includes the heterogeneous and often complex process of producing unique, large and immovable products with a supply of the resources (money, equipment, material, and labour). Unfortunately, the nature of the complexity, uncertainty and dynamics of most of the construction projects creates difficulties for even the best project managers (Duy, Ogunlana & Thi Xuan, 2004: 404). In addition, they are challenged by materials shortages, delays in supply, price fluctuations, damage and wastage, and lack of storage space (Asmara, 2015: 13; Kasim, 2011: 33; Ying, Tookey & Roberti, 2014: 263).

    Construction materials management is defined as a reduction in the amount and environmental effect of material waste generated, by reducing the amount of materials used in a construction project (Adafin, Daramola & Ayodele, 2010: 62). Construction companies, which support an integrated material management process, practise the design and construction of new structures or the re-modelling of existing structures, in order to use materials more efficiently (Kulkarni et al., 2017: 475; Muleya & Kamalondo, 2017: 5). This means that an excellent management system for handling materials from the design stage to the usage of the materials throughout the construction period contributes to the overall performance improvement of construction projects in terms of duration, budget, quality, productivity and material waste (Asmara, 2015: 13-14; Arijeloye & Akinradewo, 2016: 169; Kulkarni et al., 2017: 475).

    Construction companies that do not implement a proper materials control and management system often experience cost and time overruns, substandard work, disputes and abandonment (Adafin et al., 2010: 63; Adewuyi, 2012; Ameh & Itodo, 2013: 474). Improper materials control results in careless handling of materials, excessive expenditure on materials, profit loss for the contractor, and loss for the supplier when mishandled materials are rejected and returned (Omotosho, 2006).

    2.2 Effect of poor materials management

    PMM can have a negative impact on cost as a result of excessive waste, quality and time of work, which will affect project delivery and profitability.

    2.2.1 Effect on construction waste

    Previous research on the causes of waste reveals that it may occur at any stage of the construction process from inception, through design, construction and operation of the built facility, due to one or a combination of many factors (Muhwezi, Chamuriho & Lema, 2012: 13). Ameh and Itodo (2013: 748) believe that building material wastage on construction sites accounts for cost overruns, because the vast majority of the managers of construction projects pay hardly any attention to the effects of the generated material waste on cost overruns. Meanwhile, Osmani, Glass and Price (2008: 1149) believe that construction waste is effectively generated throughout the construction project, from beginning to completion, with the pre-construction stage accounting for a considerable amount. Table 1 summarises the origin and causes of construction waste.

     

     

    Table 2 summarises the origin and causes of construction waste that occurred on Brazilian building sites.

     

     

    The effect of PMM on materials waste is as follows:

    Increases quantities of waste.

    Negatively impacts on the waste management plan.

    Negatively impacts on the proposal for material waste recycling, recovering and disposal.

    Leads to mixing of waste.

    Makes it difficult to monitor the waste management plan.

    Makes it difficult to manage waste-related key performance indicators (KPIs).

    Makes it difficult to manage site waste management plan cost data.

    Negates the effort for minimizing materials utilisation.

    Impinges on the need to assess and identify materials waste streams.

    Makes it difficult to account for materials waste.

    Makes it difficult to implement a materials waste management policy.

    2.2.2 Effect on quality of work

    PMM has a negative impact on the quality of construction work (Ameh & Itodo, 2013: 474). Quality management in construction projects means maintaining the quality of construction works at the required standard to obtain customer's satisfaction that will bring long-term competitiveness and business survival for the companies (Khalek, Aziz & Sharabash, 2016: 391). Construction Arms worldwide are actively engaged in achieving internationally accepted quality levels to ensure sustainability in the current competitive market (Abdul-Rahman, Wang & Yap, 2010: 3744; Khalek et al., 2016: 391; Sinha, Garg & Dhall, 2016: 338). Construction firms must, therefore, provide the tools, techniques and procedures for a proper total quality control plan (Khalek et al., 2016: 391). Implementing the principles of Total Quality Management (TQM) in the construction industry is not an easy matter (Hoonakker, Carayon & Loushine, 2010: 955). Some reasons are 'the transient nature' of building and construction, the lack of standardisation, and the many parties involved. The conservative nature of the construction industry is another reason (Hoonakker et al., 2010: 955).

    To minimize the negative effect of PMM on the quality of work, construction Arms should employ a quality control and management programme that focuses on the main principles of TQM (Forbes & Ahmed, 2011: 232). These principles focus, among others, on customers, processes, teamwork, employee participation and continuous overall improvement of the Arm (Forbes & Ahmed, 2011: 232). According to Kuo and Kuo (2010: 623), construction Arms that implement a TQM plan focus on:

    Leadership ability that refers to the extent to which top management embraces the concept of total quality management in construction business implementation.

    Human resources management, where top management supports quality improvement plans, systematically provides training courses, and creates an environment in which self-directedness in goal setting and implementation are facilitated.

    Process management, where the construction industry empowers its project leaders or other professionals to manage project execution during the project planning and design process.

    Cooperation of firms' management, where the firm emphasises the measurement of the cooperation relationship with external alliances, in terms of the responsibility of quality improvement, the communication channels, and providing clear instructions of quality requirements to the cooperating firms.

    Continuous quality improvement and information on the firm's strategies in continuous quality improvement, including obtaining customers' feedback, the efficiency of gathering feedback, encouraging employees' quality improvement ideas, and providing rewards for quality improvement innovations.

    In practice, this means that construction firms with improved quality control plans are characterised by, for example, employee involvement, management commitment, a skilled workforce, communication between managers and employees, sufficient training and education, and subcontractors' involvement (Kuo & Kuo, 2010: 623). These firms also have well-defined roles and responsibilities, clearly defined goals and objectives, review/analysis used to improve performance, regular inspections and audits, incentives for good performance, regular meetings, criteria used in pre-qualification in the bidding process, and written programmes or policies (Hoonakker et al., 2010: 959).

    Construction firms that implement TQM principles in their quality control plans have the benefit of survival in an increasingly competitive world, better service to customers, and enhancement of the organisation's shareholder value (Forbes & Ahmed, 2011: 231-232). These firms improve the overall quality and safety of facilities, reduce project durations and costs, and utilize the talents of its people (Forbes & Ahmed, 2011: 231-232; Senaratne & Jayarathna, 2012: 103). All these activities will ensure that an organisation can provide a quality product at the right time, lowest cost and to the customer's specific specifications (Senaratne & Jayarathna, 2012: 103).

    Focusing on TQM, the effect of PMM on quality of work can be summarised as follows:

    Quality of work is compromised, because PMM leaves some materials spoiled.

    Impacts negatively on the quality of some of the materials on site.

    Negates the quality standard set up by management.

    Negates materials quality control.

    Makes it difficult to conduct materials quality audits.

    2.2.3 Effect on project profitability

    Construction materials contribute significantly to the cost of any project. Material wastage thus has a negative impact on construction costs, contractor's profit margin, construction duration and can be a possible source of dispute among parties to a project (Adewuyi & Odesola, 2015: 83). The primary focus of a contractor is to deliver a project safely while maximising profit. Contractors need to survive, and this is based on the profit realised as a result of their expertise (Aiyetan & Smallwood, 2013: 1162).

    Nguyen, Ogunlana and Lan (2004: 404) acknowledge that a construction project is successful when it is completed on time, within budget, in accordance with specifications, and to the stakeholders' satisfaction. Functionality, profitability to contractors, absence of claims and 'fitness for purpose' for occupiers have also been used as measures of project success.

    The generation of wastes means loss of profits to contractors, due to extra overhead costs and delays in work execution, which lead to lower productivity (Muhwezi et al., 2012: 12). Contractors and other stakeholders must, therefore, be educated and sensitized about the strategies and benefits of waste minimization on construction projects and the cost-saving measures that can be followed in waste reduction, which can ultimately result in increased profit margins (Muhwezi et al., 2012: 18).

    Materials management on site should seek to reduce loss of profit, due to theft, damage and wastage, as well as running out of stock (Kasim, Anumba & Dainty, 2005: 795). In addition, management of construction materials in building projects can raise the project profit dramatically and save considerable time (Zeb, Malik, Nauman, Hanif & Amin, 2015: 170).

    The effects of PMM on profitability are as follows:

    PMM increases waste, thus reducing profitability.

    Suboptimal accounting for materials affects profitability.

    Poor site storage of materials leads to theft of materials, resulting in low profitability.

    Poor site storage of materials leads to damage/destruction, thus reducing profitability.

    Suboptimal materials quality leads to rework and decreases profitability.

    PMM increases health and safety incidents, leading to claims/ expenses and affecting profitability.

     

    3. RESEARCH METHOD

    This study investigates the effect of PMM in the construction industry in terms of materials waste, quality, and profitability in Abuja, Nigeria. The research adopted the qualitative method of research inquiry (Cresswell, 2006: 54). Although there are several types of qualitative methods such as, for instance, narrative analysis, ethnography, phenomenology, grounded theory, the collective case study approach was deemed appropriate for this research (Cresswell, 2006: 57). In this study, direct observation in the in-depth case studies provided an understanding of the PMM on construction sites (Taylor-Powell & Steele, 1996: 1). As a research method, observation enables researchers to obtain a detailed description of social settings or events to situate people's behaviour within their own sociocultural context (Hennink, Hutter & Bailey, 2011: 170). Observation provides the opportunity to document activities, behaviour and physical aspects without depending on peoples' willingness and ability to respond to questions (Taylor-Powell & Steele, 1996: 1).

    3.1 Study area

    The assessment was based on building construction project sites in the Federal Capital Territory (FCT) of Nigeria. Abuja is within the middle belt region of Nigeria. The capital city Abuja is located within the wider Abuja Municipal Area Council. The territory is currently made up of six area councils, namely Abaji, Abuja Municipal Area Council (AMAC), Bwari, Gwagwalada, Kuje, and Kwali. AMAC is the area under study. This area consists of 11 wards, namely City Centre, Garki, Gwagwa, Gwarimpa, Jiwa, Karshi, Kabusa, Karu, Nyanya, Orozo, and Wuse. The study was carried out in the 11 wards under AMAC, but only 10 projects within the geographical area meet the purposive sampling requirement.

    3.2 Population and sample

    The population for this study is building construction sites in Abuja, the Federal Capital Territory of Nigeria, because it is one of Nigeria's metropolitan cities with the highest population of the built environment professionals in the country. It has many ongoing building construction projects, the proximity of the researcher's state of origin to the study area (FCT, Abuja), and the location of the construction projects in the same area makes the study more economical in terms of cost and time. From this population, a sample of ten building projects were selected, with a value of 100 million Naira and above, using purposive non-probability sampling techniques. The rationale for the purposive non-probability (typical case sampling selection) is that building construction projects of this value and above are typically likely to have PMM compared with projects of less value (Patton, 2002: 236).

    3.3 Data collection

    The data were sourced from ten both public and private construction project sites within Abuja, Nigeria, with a project value of up to 100 million Naira and above. Between November 2018 and February 2019, the researcher visited each of these project sites and used covert observation (no one knows that they are being observed and the observer is a concealed or embedded research) to observe and record people's behaviour, actions and interactions (McKechnie, 2008: 133). The observation was done for an average period of four hours for the four-month period.

    The study considered the majority of the building materials such as blocks/ bricks, timber, cement, reinforcement, mortar and aggregate (both fine and coarse) used in projects. These materials represent a significant percentage of the total cost of buildings in most of the traditionally built residential and commercial buildings in Nigeria. The construction processes observed included materials usage onsite, loading/offloading of materials from procurement, storages, as well as materials handling and movement on site. The site workers involved in each operation were observed.

    For data collection, based on the literature review, recording sheets with checklists were pre-set with statements (Likert items) and responses to observe and document the effect of PMM related to material waste, quality, and profitability. Recording sheet 1 consists of 11 statements (Likert items) on the effect of PMM on materials waste. The observer rated quantities of waste, waste management plan, waste recycling and disposal, mixing, KPI, costs, utilisation, waste streams, account waste, and waste policy in terms of materials usage onsite, loading/offloading of materials from procurement, storages, as well as materials handling and movement on site. Recording sheet 2 consists of five statements (Likert items) on the effect of PMM on quality. The observer rated spoiled materials, onsite materials quality, standards, control, and audits in terms of the materials usage onsite, loading/offloading of materials from procurement, storages, as well as materials handling and movement on site. Recording sheet 3 consists of six statements (Likert items) on the effect of PMM on profitability. The observer rated increased waste, suboptimal accounting, theft, damaged materials, rework, health and safety claims in terms of the materials usage onsite, loading/offloading of materials from procurement, storages, as well as materials handling and movement on site. For the purpose of anonymity, the names of the project sites are not disclosed in this article. Instead, they are represented by case study (CS) numbers CS1-CS10.

    3.4 Data analysis and interpretation

    The Statistical Package for the Social Sciences (SPSS) version 23 was used to conduct descriptive analysis of the data computing the mode that describes the most frequently occurring effect of PMM in construction (Field, 2013).

    To measure the central tendency of the effect of PMM on materials waste, quality and profitability, the statements (Likert items) were rated on an ordinal three-point Likert scale. Likert-type scales use fixed choice response formats and are designed to measure the strength of the researcher's perceived agreement or disagreement with statements (Likert items) (Schmee & Oppenlander, 2010: 14). The following scale measurement was used regarding modal value, where 1 = high effect; 2 = moderate effect, and 3 = low effect.

    3.5 Limitation(s) of the study

    This research focuses on the effect of PMM in building projects in Abuja, Federal Capital Territory of Nigeria. This article only focuses on knowing the level of effects of PMM on waste generation, quality and profitability. Subsequent research will address the mitigation strategies. This research uses observation of what was observed on site with the observation guide by the observer (researcher). No interviews were conducted. Thus, the voice of the contractor/consultants was not considered.

     

    4. RESULTS AND DISCUSSION

    4.1 Effect of poor materials management on materials waste

    An overall model value of 3 (see Table 3) demonstrates that PMM has a high effect on material waste in the construction industry in Abuja, Nigeria.

     

     

    This means that PMM exacerbates the problem of wastage of materials on sites.

    The results show that PMM increases the quantity of materials waste. This finding was supported by Saidu and Shakantu (2016: 106) that imprudent materials management does increase material waste on construction sites, with an additional result of a corresponding increase in the amount of cost overrun for a project. In addition, material waste has a significant impact on the cost of a project as well as an adverse impact on the environment (Nagapan, Rahman, Asmi, Memon & Latif, 2012: 325). The study found that a waste management plan has a high effect on construction site materials wastage. This finding corroborates studies by Tam (2008: 1074), Bossink & Brouwers (1996: 57), Faniran & Caban (1998: 183), and Osmani et al. (2008: 1149), as highlighted in Table 1.

    It is important to understand what wastes are likely to be generated and then focus on how the generation of those wastes can be avoided or minimized. Regarding monitoring of the waste management plan, it was observed that PMM negatively impacts on the waste management plan. This corroberates the findings of Dania, Kehinde and Bala (2007: 128) that site materials waste management is very poor and has much room for improvement. A waste management plan, therefore, provides an idea about different kinds of waste and how they can be managed to ensure minimal to no negative effect on the construction project. Effective waste management approaches could reduce the negative impact of the construction industry on the environment.

    Mixing of waste also had a negative effect on the construction sites. This corroborates the report of Cox (2018) that mixing waste for disposal makes it almost impossible to meet the organisation's waste management targets. The mixing of waste on sites should be avoided, as it is difficult to separate the waste at a later stage. Efforts at minimising materials utilisation, site waste management plan cost data and a waste management policy had a moderate to high effect on the control of materials wastage. It is imperative to determine the waste-related KPIs that are best for construction projects, because it is evident from the results in Table 3 that waste-related KPIs have a high effect on materials waste on construction sites. This means that the management teams selected the right KPI for the construction companies. This finding supports a study by Chan and Chan (2004: 203), which established that, in order to identify the 'real' success factors of construction projects, it is important to identify parameters (KPIs) for benchmarking projects at the project selection phase, in order to achieve good project performance.

    PMM has a low effect on materials waste streams, because waste is not sorted into specific streams, from its source through to recovery, recycling or disposal process on construction projects. This implies that PMM has a negative effect on construction projects. This contradicts a report by Towing (1998) that recycling and controlled management of construction waste streams would save land and create better opportunities for handling other kinds of waste.

    In this context, managing materials waste means eliminating waste, where possible, minimising waste, where feasible, and reusing materials that might otherwise become waste. Therefore, producing a site waste management plan before the start of a construction project would help achieve good practice waste management.

    4.2 Effect of poor materials management on quality

    An overall modal value of 2 (see Table 4) demonstrates that PMM has a moderate effect on quality in the construction industry in Abuja, Nigeria.

     

     

    It is clear from Table 4 that the statement "poor materials management negates materials quality control" was considered to have a high effect on quality, since it has a modal value of 3. This is in tandem with the findings of Khalek et al. (2016: 394) on achieving quality in materials management in construction projects. Quality control is that part of quality management that ensures that products and services comply with requirements and standards. One way of controlling quality is based on the inspection or verification of products.

    The statements with moderate effects on quality were: PMM impacts negatively on the quality of some of the materials on site; PMM negates

    the quality standard set up by management, and PMM makes it difficult to conduct materials quality audits. These were considered to have moderate effects on quality, because they all have modal values of 2. These results corroborate the findings of Khalek et al. (2016: 394), who highlighted that onsite delivery of substandard materials and products is one of the major problems impacting negatively on the quality of materials on site.

    A quality audit is a review of how well the key areas of the project quality plan are being followed. The purpose of the audit is to determine whether the quality plan is working as intended. To achieve a successful materials quality audit, first, the correct procedures specified in the quality plan should be followed and, secondly, they should be followed consistently (Oakland, 2014; Dale, Van Der Wiele & Van Iwaarden, 2007; Juran, 1999).

    It is the responsibility of the contractor to assure the client of continuous conformity with the appropriate standards and regulations, and to conduct quality control through self-inspection, quality assurance, quality directing, and quality auditing.

    4.3 Effect of poor materials management on profitability

    Overall modal values of 2 and 3 (see Table 5) demonstrate that PMM has a moderate to high effect on profitability in the construction industry in Abuja, Nigeria.

     

     

    The reason why contractors fail to achieve their desired profitability after winning a contract is that the materials required to complete the project are not managed properly during the construction period (Kerzner, 2002).

    It was found that PMM increases waste, thus reducing profitability of construction projects. This means that materials waste on site reduces the contractors' profits. This corroborates the submission that prevention and managing the causes of wastage may help reduce the impact on the project and increase profits (Ahankoob, Khoshnava, Rostami & Preece 2012: 196). There is a need to reduce materials waste on site, in order to achieve profitability.

    The research also found that PMM has a moderate to high effect on suboptimal accounting for materials, thus affecting profitability. This supports Wahab and Lawal's (2011: 252) finding that there is a lack of record-keeping of materials supplied and used on site, thus affecting profitability. Therefore, proper records of materials receiving, and materials requisition should be kept, and materials monitoring should be done.

    Another high effect of PMM is on-site storage of materials, which leads to theft of materials and reduced profitability. Missing materials due to theft need to be replaced by new materials, thus reducing profitability.

    Another high effect of PMM was on poor site storage of materials, which leads to damage/destruction and reduces the profitability of construction projects. This finding agrees with Kasim et al. (2005: 795), as highlighted in section 2.2.3 of this study. This means that, if adequate storage of materials is not put in place and if there is damage/destruction, more material is needed to replace the damaged/destroyed materials, thus decreasing profitability.

    There is a moderate effect in terms of how PMM increases suboptimal materials quality, which leads to rework and decreases profitability. Rework could adversely affect time and productivity and, ultimately, also profitability. These results are in line with the findings of Sun and Meng (2009: 560), Aiyetan (2013: 2), as well as Hughes and Thorpe (2014: 223), that the direct impacts of rework on construction projects would likely include additional time for rework; additional costs for covering rework occurrences; additional materials for rework and subsequent wastage handling, and additional labour for rework and related extensions of supervision manpower. All these studies agree that rework in construction projects has the potential to make at least a moderate contribution to the total project cost and to decrease profitability.

    In addition, the study found that PMM has a high effect on the occurrence of health and safety incidents, leading to claims/expenses and affecting profitability. This finding agrees with Muhwezi et al.'s (2012: 11) assertion that materials waste on building projects caused not only financial setbacks to contractors, but also significant health incidents. During this study, it was observed that construction workers on sites lacked appropriate protective equipment. For example, workers were observed carrying out activities such as painting, excavations and concreting without the right protective gear such as helmets, masks, ear muffs, goggles, and overalls. There are always claims/expenses for health and safety incidents on site whenever they occur.

     

    5. CONCLUSION AND RECOMMENDATIONS

    This article investigated the effect of PMM on materials waste, quality of work and project profitability in the Nigerian construction industry.

    The study's findings revealed that PMM has a high effect on material waste generation on any construction project site, with the following statements: PMM makes it difficult to implement materials waste management policy; to account for materials waste; to manage site waste management plan cost data; to manage waste-related KPIs; negatively impacts the waste management plan and increases quantities of waste.

    The study also found that PMM has a moderate effect on the quality of building projects in Abuja, with the following statements: PMM impacts negatively on the quality of some of the materials on site; negates the quality standard set up by management and makes it difficult to conduct materials quality audits.

    In terms of profitability, it was found that PMM has both high and moderate effects on profitability in the construction industry in Abuja, Nigeria. The statements were: PMM increases waste, thus reducing profitability, and PMM leads to suboptimal accounting for materials, thus affecting profitability.

    Based on these findings, it can be concluded that effective management of materials in construction projects would reduce the amount of waste generation, increase the quality of construction work, and result in optimum profitability to construction contractors.

    It is, therefore, recommended that the construction industry in Nigeria should collaborate with government agencies to develop guidelines for preparing a waste management plan for the construction industry and ensure that top management adopts the culture of training and developing their staff about new managerial tools and techniques for site materials management.

     

    REFERENCES

    Abdul-Rahman, H., Wang, C. & Yap, X.W. 2010. How professional ethics impact construction quality: Perception and evidence in a fast-developing economy. Scientific Research and Essays, 5(23), pp. 3742-3749.         [ Links ]

    Adafin, J.K., Daramola, O. & Ayodele, E.O. 2010. Study of material control strategies in some selected construction firms in Nigeria. Continental Journal of (online) Sustainable Development, vol. 1, pp. 62-72.         [ Links ]

    Adewuyi, T.O. 2012. Construction material waste planning and control techniques on building sites in South-South of Nigeria. Unpublished PhD thesis, Department of Building, Faculty of Environmental Studies, University of Uyo, Nigeria.         [ Links ]

    Adewuyi, T.O. & Odesola, I.A. 2015. Factors affecting material waste on construction sites in Nigeria. Journal of Engineering and Technology (JET), 6(1), pp. 82-99.         [ Links ]

    Ahankoob, A., Khoshnava, S.M., Rostami, R. & Preece, C. 2012. BIM perspectives on construction waste reduction. In: Proceedings of the Management in Construction Research Association (MiCRA) Postgraduate Conference, 5-6 December 2012, Kuala Lumpur, Malaysia: UTM, pp. 195-199.         [ Links ]

    Aiyetan, A.O. 2013. Causes of rework on building construction projects in Nigeria. Interim: Interdisciplinary Journal, 12(3), pp. 1-15. https://doi.org/10.32738/CEPPM.201310.0102        [ Links ]

    Aiyetan, A.O. & Smallwood, J.J. 2013. Materials management and waste minimisation on construction sites in Lagos State, Nigeria. In: Proceedings of the 4 International Conference on Engineering, Project, and Production Management (EPPM), 23-25 October 2013, Bangkok, Thailand: The Sukosol, pp. 1161-1172.         [ Links ]

    Albert, I. 2014. Assessment of professional's perception on materials management practices on construction sites in selected states in Nigeria. Unpublished Masters dissertation. Zaria: Ahmadu Bello University.         [ Links ]

    Albert, I. & Shakantu, W. 2017. An investigation of materials management on sustainable construction in Nigeria. International Journal of Innovative Research in Technology, Basic and Applied Sciences, 4(1), pp. 8-17.         [ Links ]

    Ali, S.A.A., Arun, C. & Krishnamurthy, K. 2017. New approach of direct and indirect time waste in civil construction engineering. International Journal of Civil Engineering and Technology, 8(12), pp. 817-832.         [ Links ]

    Alwan, Z., Jones, P. & Holgate, P. 2017. Strategic sustainable development in the UK construction industry, through the framework for strategic sustainable development, using Building Information Modelling. Journal of Cleaner Production, 140(1), pp. 349-358. https://doi.org/10.1016/j.jclepro.2015.12.085        [ Links ]

    Ameh, J.O. & Itodo, E.D. 2013. Professionals' views of material wastage on construction sites. Organization, Technology and Management in Construction. An International Journal, 5(1), pp. 747-757. https://doi.org/10.5592/otmcj.2013.1.11        [ Links ]

    Arijeloye, B.T. & Akinradewo, F.O. 2016. Assessment of materials management on building projects in Ondo State, Nigeria. World Scientific News, vol. 55, pp.168-185.         [ Links ]

    Asmara, S. 2015. Managing and minimizing wastage of construction materials on selected public building projects in Addis Ababa. Unpublished Master's thesis. Ethiopia, Addis Ababa University.         [ Links ]

    Aziz, R.F. & Hafez, S.M. 2013. Applying lean thinking in construction and performance improvement. Alexandria Engineering Journal, 52(4), pp. 679695. https://doi.org/10.1016/j.aej.2013.04.008        [ Links ]

    Bossink, B.A.G. & Brouwers, H.J.H. 1996. Construction waste: Quantification and source evaluation. Journal of Construction Engineering and Management, 122(1), pp. 55-60. https://doi.org/10.1061/(ASCE)0733-9364(1996)122:1(55)        [ Links ]

    Butera, S., Christensen, T.H. & Astrup, T.F. 2015. Life cycle assessment of construction and demolition waste management. Waste Management, vol. 44, pp. 196-205. https://doi.org/10.1016/j.wasman.2015.07.011        [ Links ]

    Chan, A.P. & Chan, A.P. 2004. Key performance indicators for measuring construction success. Benchmarking: An International Journal, 11(2), pp. 203-221. https://doi.org/10.1108/14635770410532624        [ Links ]

    Clough, R.H., Sears, G.A. & Sears, S.K. 2000. Construction project management. New York: John Wiley and Sons.         [ Links ]

    Cox, M. 2018. Waste management in construction sector. PPT presentation. International Institute of Risk and Safety Management. [Online]. Available at: <https://www.iirsm.org/sites/default/flles/Waste%20Management.pdf> [Accessed: 12 March 2019].         [ Links ]

    Cresswell, J.W. 2006. Qualitative inquiry and research design. Thousand Oaks, CA: Sage.         [ Links ]

    Dale, B.G., Van Der Wiele, T. & Van Iwaarden, J. 2007. Managing quality. New York: John Wiley & Sons.         [ Links ]

    Dallasega, P. & Rauch, E. 2017. Sustainable construction supply chains through synchronized production planning and control in engineer-to-order enterprises. Sustainability, 9(10), article nr. 1888, pp. 1-25. https://doi.org/10.3390/su9101888        [ Links ]

    Dania, A.A., Kehinde, J.O. & Bala, K. 2007. A study of construction material waste management practices by construction Arms in Nigeria. In: Proceedings of the 3rd Scottish Conference for Postgraduate Researchers of the Built and Natural Environment, Glasgow, UK: Glasgow Caledonian University, pp. 121-129.         [ Links ]

    Doloi, H., Sawhney, A., Iyer, K.C. & Rentala, S. 2012. Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), pp. 479-489. https://doi.org/10.1016/j.ijproman.2011.10.004        [ Links ]

    Duy Nguyen, L., Ogunlana, S.O. & Thi Xuan Lan, D. 2004. A study on project success factors in large construction projects in Vietnam. Engineering, Construction and Architectural Management, 11(6), pp. 404413. https://doi.org/10.1108/09699980410570166        [ Links ]

    Ekanayake, L.L. & Ofori, G. 2004. Building waste assessment score: Design-based tool. Building and Environment, 39(7), pp. 851-861. https://doi.org/10.1016/j.buildenv.2004.01.007        [ Links ]

    Faniran, O.O. & Caban, G. 1998. Minimizing waste on construction project sites. Engineering, Construction and Architectural Management, 5(2), pp. 182-188. https://doi.org/10.1046/j.1365-232X.1998.00044.x        [ Links ]

    Field, A. 2013. Discovering statistics using IBM SPSS statistics. 4th edition. Thousand Oaks, CA: Sage.         [ Links ]

    Forbes L.H. & Ahmed S.M. 2011. Modern construction - Lean project delivery and integrated practices. Boca Raton, FL: CRC Press. https://doi.org/10.1201/b10260        [ Links ]

    Formoso, C.T., Isatto, E.L. & Hirota, E.H. 1999. Method for waste control in the building industry. In: Proceedings IGLC (vol. 7), 26-28 July, University of California, Berkeley, CA, pp. 325-334.         [ Links ]

    Gürcanli, G.E. & Müngen, U. 2013. Analysis of construction accidents in Turkey and responsible parties. Industrial Health, 51(6), pp. 581-595. https://doi.org/10.2486/indhealth.2012-0139        [ Links ]

    Hennink, M., Hutter, I. & Bailey, A. 2011. Qualitative research methods. London: Sage.         [ Links ]

    Hoonakker, P., Carayon, P. & Loushine, T. 2010. Barriers and benefits of quality management in the construction industry: An empirical study. Total Quality Management, 21(9), pp. 953-969. https://doi.org/10.1080/14783363.2010.487673        [ Links ]

    Hughes, R. & Thorpe, D. 2014. A review of enabling factors in construction industry productivity in an Australian environment. Construction Innovation, 14(2), pp. 210-228. https://doi.org/10.1108/CI-03-2013-0016        [ Links ]

    Juran, J.M. 1999. How to think about quality. In: Juran, J.M., Godfrey, A.B., Hoogstoel, R.E. & Schilling, E.G. (Eds). Juran's quality handbook. New York: McGraw-Hill, pp. 2.1-2.18.         [ Links ]

    Kasim, N. 2011. ICT implementation for materials management in construction projects: Case studies. Journal of Construction Engineering and Project Management, 1(1), pp. 31-36. https://doi.org/10.6106/JCEPM.2011.1.1.031        [ Links ]

    Kasim, N., Latiffi, A.A. & Fathi, M.S. 2013. RFID technology for materials management in construction projects - A review. International Journal of Construction Engineering and Management, 2(A), pp. 7-12.         [ Links ]

    Kasim, N.B., Anumba, C.J. & Dainty, A.R.J. 2005. Improving materials management practices on fast-track construction projects. In: Khosrowshahi, F. (Ed.). Proceedings of the 21st Annual ARCOM Conference, 7-9 September, University of London: SOAS, pp. 793-802.         [ Links ]

    Kerzner, H. 2002. Strategic planning for project management using a project management maturity model. New York: John Wiley & Sons.         [ Links ]

    Khalek, H.A., Aziz, R.F. & Sharabash, E.A. 2016. Applications and assessment of quality management in construction projects. International Journal of Innovative Research in Engineering & Management, 3(5), pp. 391-402.         [ Links ]

    Kulkarni, V., Sharma, R. & Hote, M. 2017. Factors affecting material management on construction site. International Research Journal of Engineering and Technology, 4(1), pp. 474-478.         [ Links ]

    Kuo, T.H. & Kuo, Y.L. 2010. The effect of corporate culture and total quality management on construction project performance in Taiwan. Total Quality Management, 21(6), pp. 617-632. https://doi.org/10.1080/14783363.2010.483074        [ Links ]

    Llatas, C. 2011. A model for quantifying construction waste in projects according to the European waste list. Waste Management, 31(6), pp. 12611276. https://doi.org/10.1016/j.wasman.2011.01.023        [ Links ]

    Lu, W. & Yuan, H. 2011. A framework for understanding waste management studies in construction. Waste Management, 31(6), pp. 1252-1260. https://doi.org/10.1016/j.wasman.2011.01.018        [ Links ]

    McKechnie, L.E.F. 2008. Covert observation. In: Given, L.M (Ed.). The SAGE encyclopedia of qualitative research methods. Thousand Oaks, CA: Sage, pp. 133-135.         [ Links ]

    Muhwezi, L., Chamuriho, L.M. & Lema, N.M. 2012. An investigation into materials wastes on building construction projects in Kampala-Uganda. Scholarly Journal of Engineering Research, 1(1), pp. 11-18.         [ Links ]

    Muleya, F. & Kamalondo, H. 2017. An investigation of waste management practices in the Zambian construction industry. Journal of Building Construction and Planning Research, 5(1), pp. 1-13. https://doi.org/10.4236/jbcpr.2017.51001        [ Links ]

    Nagapan, S., Rahman, I.A., Asmi, A., Memon, A.H. & Latif, I. 2012. Issues on construction waste: The need for sustainable waste management. In: Proceedings of the IEEE Colloquium on Humanities, Science and Engineering (CHUSER 2012), 3-4 December, Kota Kinabalu, Sabah, Malaysia: IEEE, pp. 325-330. https://doi.org/10.1109/CHUSER.2012.6504333        [ Links ]

    Nguyen Duy, L., Ogunlana, S.O. & Thi Xuan Lan, D. 2004. A study on project success factors in large construction projects in Vietnam. Engineering, Construction and Architectural Management, 11(6), pp. 404-413. https://doi.org/10.1108/09699980410570166        [ Links ]

    Oakland, J.S. 2014. Total quality management and operational excellence: Text with cases. 4th edition. London: Routledge.         [ Links ]

    Omotosho, K.P. 2006. An investigation into material control system on construction sites in Nigeria. Unpublished PGD dissertation. Department of Quantity Surveying, The Federal University of Technology, Akure.         [ Links ]

    Osmani, M., Glass, J. & Price, A.D. 2008. Architects' perspectives on construction waste reduction by design. Waste Management, 28(7), pp. 1147-1158. https://doi.org/10.1016/j.wasman.2007.05.011        [ Links ]

    Patel, K.V. & Vyas, C.M. 2011. Construction materials management on project sites. In: National Conference on Recent Trends in Engineering & Technology (NCRTET - 2011), 13-14 May, Anand, Gujarat, India: BVM Engineering College, Vallabh Vidyanagar, pp. 1-5.         [ Links ]

    Patton, M.Q. 2002. Qualitative research and evaluation methods. 3rd edition. Thousand Oaks, CA: Sage.         [ Links ]

    Pérez, C.T. & Costa, D. 2018. Developing a taxonomy of transportation waste in construction production processes. Built Environment Project and Asset Management, 8(5), pp. 434-448. https://doi.org/10.1108/BEPAM-04-2018-0062        [ Links ]

    Rajendran, P. & Gomez, C.P. 2012. Implementing BIM for waste minimization in the construction industry: A literature review. In: 2nd International Conference on Management (2nd ICM 2012), 11-12 June, Kedah, Malaysia, pp. 557-570.         [ Links ]

    Saidu, I. & Shakantu, W. 2016. The contributions of construction material waste to project cost overruns in Abuja, Nigeria: Review article. Acta Structilia, 23(1), pp. 99-113. https://doi.org/10.18820/24150487/as23iL4        [ Links ]

    Schmee, J. & Oppenlander, J. 2010. Means business: Statistical models for management. Cary, NC: SAS Institute Inc.         [ Links ]

    Senaratne, S. & Jayarathna, T. 2012. Quality planning process of construction contractors: Case studies in Sri Lanka. Journal of Construction in Developing Countries, 17(1), pp. 103-115.         [ Links ]

    Sinha, N., Garg, A.K. & Dhall, N. 2016. Effect of TQM principles on performance of Indian SMEs: The case of automotive supply chain. The TQM Journal, 28(3), pp. 338-359. https://doi.org/10.1108/TQM-10-2014-0086        [ Links ]

    Sun, M. & Meng, X. 2009. Taxonomy for change causes and effects in construction projects. International Journal of Project Management, 27(6), pp. 560-572. https://doi.org/10.1016/j.ijproman.2008.10.005        [ Links ]

    Tam, V.W. 2008. On the effectiveness in implementing a waste-management-plan method in construction. Waste Management, 28(6), pp. 1072-1080. https://doi.org/10.1016/j.wasman.2007.04.007        [ Links ]

    Taylor-Powell, E. & Steele, S. 1996. Collecting evaluation data: Direct observation. G 3658-5 Program Development and Evaluation. Madison, WI: University of Wisconsin-Extension, pp. 1-7.         [ Links ]

    Towing, M., 1998. Management of construction and demolition waste streams. In: Proceedings of the CIB World Building Congress, 7-12 June, Gävle, Sweden, pp. D525.         [ Links ]

    Ugochukwu, S., Agugoesi, S., Mbakwe, C. & Abazuonu, L. 2017. An on-site quantification of building material wastage on construction projects in Anambra State, Nigeria: A comparison with the literature. Journal of Civil Engineering and Architecture, 3(6), pp. 12-23.         [ Links ]

    Ugwu, O.O. & Attah, I.C. 2016. An appraisal of construction management practice in Nigeria. Nigerian Journal of Technology, 35(4), pp. 754-760. https://doi.org/10.4314/njt.v35i4.9        [ Links ]

    Wahab, A.B. 2010. Stress management among artisans in construction industry in Nigeria. Global Journal of Researches in Engineering, 10(1), pp. 93-103.         [ Links ]

    Wahab, A.B. & Lawal, A.F. 2011. An evaluation of waste control measures in construction industry in Nigeria. African Journal of Environmental Science and Technology, 5(3), pp. 246-254.         [ Links ]

    Ying, F., Tookey, J. & Roberti, J. 2014. Addressing effective construction logistics through the lens of vehicle movements. Engineering, Construction and Architectural Management, 21(3), pp. 261-275. https://doi.org/10.1108/ECAM-06-2013-0058        [ Links ]

    Zaneldin, E.K. 2006. Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5), pp. 453-459. https://doi.org/10.1016/j.ijproman.2006.02.006        [ Links ]

    Zeb, A., Malik, S., Nauman, S., Hanif, H. & Amin, O.S. 2015. Factors affecting material procurement, supply and management in building projects of Pakistan: A contractor's perspective. In: Proceedings of the International Conference on Innovations in Civil and Structural Engineering (ICICSE'15), 3-4 June, Istanbul, Turkey, pp. 170-175.         [ Links ]

     

     

    Received: September 2018
    Peer reviewed and revised: February 2019
    Published: June 2021

     

     